Why I don’t agree with quantifying risk

Aug 27

5 min read

0

13

1



I am writing this following a LinkedIn comment that misunderstood what I was trying to say about Bowties. In my opinion, a bowtie is a useful model to incorporate into a wider report, Safety Case or “Well Reasoned Argument” (WRA). I also believe the shortcomings of “measuring” risk on a matrix are myriad, not least because of how they cause people to perceive risk and influence the adoption of mitigations.

 

In the industries I have worked in, the risk matrix is ubiquitous; so when asked what I thought the advantage a 5x5 risk matrix was over a 4x5, it started me thinking.  A risk matrix is meant to help categorise, prioritise and compare risks, so what difference does 5 or 4 rows or columns really make?  I thought it would depend on how precisely the severity and likelihood ranges have been defined but what I found out was so much more.

 

I have always been mildly sceptical of risk matrices, struggling to see how all that risk data could be condensed and simplified into a single box, and still remain meaningful.  It turns I was right to be doubtful!

 

My research highlighted that there is no scientific method for designing the scale used in a risk matrix.  From the numerous and varied scales I have encountered in aviation and elsewhere, the common factor is they are typically ordinal scales. An ordinal scale has no fixed distance between the levels; the numbers represent a rank position.  Questions with subjective responses are often ordinal, for example, “how much pain are you in?” could be answered with “none”, “a little”, “some”, “a lot”, “excruciating”.  The responses go from least to most pain, but it’s not clear whether the difference between “none” and “a little” is bigger, smaller, or the same as the difference between “a lot” and “excruciating”.  This also emphasises the subjective nature of the scale.  What’s excruciating to me maybe merely “a little painful” to you.

 

Ordinal responses may be transformed in any way that preserves their order, which in a 5x5 risk matrix could be 1-5 or 0,5,37,40 and 103.  The numbers are irrelevant as long as the order stays the same.

Using the previous example,  it’s obvious that “excruciating” is not twice as painful as “some”.  Like 70 degrees is not twice as hot as 35 degrees.  Multiplication cannot be applied to an ordinal scale, but this is what appears to have been done in the CAA UK’s CAP 795, Safety Management Systems (SMS) guidance for organisations.  The numbers are drawing incorrect comparisons between risks, suggesting that Remote/hazardous is twice as risky as improbable/major, as a result of committing the mathematical no-no of multiplying an ordinal scale.

Cox has written extensively about the use of risk matrices and investigates how the use of ordinal scales can lead to errors in decision making.  For me, he has named one of the most significant errors “range compression” which can lead to risks with significantly different values being placed in the same cell.  Consider ICAO’s “Example safety risk severity table” (table 1).  The boundary between hazardous and catastrophic is blurred because there is nowhere to categorise a single, or a “few” deaths.  For example, the risk of one or two deaths would have to be categorised alongside total hull loss resulting in mass casualties, which feels wrong to me.

Severity

Meaning

Value

Catastrophic

·        Aircraft /equipment destroyed

·        Multiple deaths

A

Hazardous

·        A large reduction in safety margins, physical distress or a workload such that operational personnel cannot be relied upon to perform their tasks accurately or completely

·        Serious injury

·        Major equipment damage

B

Major

·        A significant reduction in safety margins, a reduction in the ability of operational personnel to cope with adverse operating conditions as a result of an increase in workload or as a result of conditions impairing their efficiency

·        Serious incident

·        Injury to persons

C

Minor

·        Nuisance

·        Operating limitations

·        Use of emergency procedures

·        Minor incident

D

Negligible

·        Few consequences

E

Table 1 - Example safety risk severity table (from ICAO Doc 9859, Safety Management Manual, Fourth edition, 2018)


CAA UK has thankfully reversed ICAO’s counterintuitive matrix (table 2) and refined the hazardous category to a certain extent by adding “serious injury or death to a number of people”, but the risk ranking still seems arbitrary.  A risk that is likely to occur many times with a nuisance outcome is given higher priority (10) than a risk that may possibly occur and will result in serious injury to persons (9).  The possible occurrence of death to a number of people is ranked the same (12) as a significant reduction in safety margins that has occurred infrequently.  The relative magnitude of consequences and probability is compressed, thus undermining the readily held belief that risk matrices improve communication.


Table 2 – CAA UK Example risk tolerability matrix

 




 

Thomas, Reidar and Bratvold talk about centring bias, a phenomenon in which 75% of the probability ratings assessed were centred around 2,3 and 4, thereby effectively reducing the matrix to a 3x3!  Also, probability ratings are often necessarily ambiguous and open to interpretation.  A study by Budescu et al (2009) showed that “very likely” was assigned to probabilities varying from 0.43 to 0.99 because context and personal attitude to risk will always influence a person’s perception of consequence.  Additionally,  the words used to describe probability (compare these two definitions of improbable: “virtually improbable and unrealistic” with “ would require a rare combination of factors to cause an incident”) lead to inconsistencies.

Before summing up, I give you an interesting extract from Cox’s paper:“..the common assumption that risk matrices, although imprecise, do some good in helping to focus attention on the most serious problems and in screening out less serious problems is not necessarily justified. Although risk matrices can indeed be very useful if probability and consequence values are positively correlated, they can be worse than useless when probability and consequence values are negatively correlated. Unfortunately, negative correlation may be common in practice, for example, when the risks of concern include a mix of low-probability, high consequence and higher-probability, low-consequence events”.

So what’s the alternative, given that risk matrices are so entrenched in our risk management practices?  First, we need to recognise the limitations of risk matrices and educate ourselves so we are in a position to explain why they do not necessarily support good risk management decisions and by association, the effective allocation of resources. 

Secondly, time spent pondering whether the probability is 3 or 4 should be invested in mapping out possible accident scenarios, in identifying the critical controls and ensuring they are adequate and reliable.

This will allow us to assign priorities to barriers and assess whether the effectiveness of the barrier is tolerable, rather than prioritising and categorising a set of risks based on a flawed matrix. 


Ball, D.J. and Watt, J. (2013) Further thoughts on the utility of risk matrices. Risk Analysis. Vol 33, 11.


Budescu, D.V., Broomell, S., and Por, H.H. (2009).  Improving communication of uncertainty in reports of the intergovernmental panel on climate change.  Psychological Science.  20, 3:299-308.


Cox Jr., L.A. (2008). What’s wrong with Risk Matrices?  Risk Analysis.  Vol 28, 2.


Hubbard, D. W., Seiersen, R. (2016)  How to Measure Anything in Cybersecurity Risk. Wiley:New Jersey

 

ICAO Doc 9859 Safety Management Manual (2018) Fourth edition


Safety and Airspace Regulation Group. (2015). CAP 795 Safety Management Systems (SMS) guidance for organisations. CAA UK.


Thomas, P. Bratvold, R.B. and Bickel, J.E. (2013) The Risk of Using Risk Matrices.  SPE Economics and Management.


 

Aug 27

5 min read

0

13

1

Comments (1)

Thank you for such a comprehensive explanation of your thoughts Emily, I tend to agree with your argument here. An example which stood out to me as a young Air Traffic Controller was that the MOD considered 10 deaths in an accident to be qualified as a disaster, while 9 was not. This very much relates to risk acceptance too, where using a matrix (of whatever number), managers will or will not accept a risk dependent on the perceived risk classification. There is often pressure to drive a specific risk to an "acceptable" letter or number, when perhaps the inputs to get to that number or letter are not fully understood or quantifiable in such a way. This is why I tend to use as much data as I can when forming a safety argument. From my own experience, I feel far happier when utilising several safety methods simultaneously on a project, such as Bowtie, LTA, FFFR, FMECA and Goal-Structured Notation in order to deliver as effective a safety argument as can be defined. Thank you